Second staircase regulations: what the Approved Document B changes mean for your scheme
The second staircase regulations in Approved Document B changed on 30 September 2026. New blocks of flats with a top storey of 18 metres or more should now have more than one common stair, and schemes already underway can only keep the old guidance if they meet the transitional rules.
If you have a residential scheme in design or on site, the key question is which version applies. That depends on when building control was notified and how far work has got, not on your planning consent date.
Second staircase regulations: what changed on 30 September 2026
The amended Approved Document B came into force in England on 30 September 2026. Its headline change is that blocks of flats with a top storey 18 metres or more in height should be served by more than one common stair.
Approved Document B is statutory guidance, so the second stair is strictly a recommendation rather than a legal rule. A design that departs from it has to show another way of achieving the same level of safety, and building control will expect strong evidence.
The update also restructures the escape guidance and explains how evacuation lifts should be designed where they are provided. It does not make evacuation lifts compulsory.
Can your scheme still use the old guidance?
Some schemes can carry on under the previous version, but only if they pass two tests set out in Circular 04/2024.
First, a building notice, initial notice or full plans application must have gone to the relevant authority before 30 September 2026. Second, the work must have started and been sufficiently progressed, either before that date or within the 18 months that follow it.
A scheme needs to pass both. Planning permission on its own does not protect a development, however early it was granted.
What sufficiently progressed means
The circular defines this closely. Work counts as sufficiently progressed when:
- for a new building, concrete has started to be poured for permanent trench, pad or raft foundations, or permanent piling has started
- for work to an existing building, that work has started
- for a material change of use, work to bring about the change has started.
Site set-up and enabling works are not enough. Keep a clear record of submission dates and progress on site, and confirm anything uncertain with your building control body.
Which buildings are affected?
The recommendation applies to blocks of flats where the top storey is 18 metres or more above ground. Height is measured from the lowest ground level next to the building to the floor surface of the top storey, as shown in Diagram D6 of Approved Document B. Roof-top plant areas are left out.
This is not the same as the higher-risk building test under the Building Safety Act. That regime covers buildings at least 18 metres high or with at least seven storeys that contain two or more homes, along with hospitals and care homes of that size. It uses its own measuring rules, so check the two questions separately.
Do interlocked stairs meet the second staircase regulations?
No. Approved Document B treats interlocked, or scissor, stairs as a single escape route. They save space, but they do not give residents an alternative way out, so any design relying on one should be reviewed.
How a second staircase changes a scheme
Adding a protected stair affects far more than the core. It can reshape:
- flat and corridor layouts
- lifts, lobbies and smoke control
- risers and service routes
- structural openings and framing
- fire stopping and compartmentation.
A larger core also means less saleable or lettable space and sometimes fewer flats, which feeds straight into viability.
This is where joined-up input pays off. Our fire engineering and building safety, architecture, structural engineering and building services teams can test layouts together, while quantity surveying shows what each option does to cost. Changes made at design stage cost far less than changes made on site.
Higher-risk buildings and Gateway 2
Programme risk is highest on higher-risk buildings, where work cannot start until the Building Safety Regulator has given Gateway 2 approval.
A scheme that applied in time can still miss the 18-month window if approval takes longer than planned. Plan the transition date and Gateway 2 together, and check how much slack is left. An experienced principal designer can spot these clashes before they become critical.
Will a second stair affect your planning permission?
It might, as an extra stair can change layouts, elevations or unit numbers. That does not always mean a new application. A non-material or minor material amendment may be enough, while bigger changes could need a fresh application. Speak to the planning authority early and get town planning advice if the route is unclear.
London schemes may be better placed, as the Mayor of London began asking for second stairs on tall residential buildings at the planning stage in 2023.
What is next for Approved Document B?
More change is on the way. In spring 2026, the Building Safety Regulator consulted on further updates covering evacuation lifts, external walls and balconies, combustible structural elements, solar panels on roofs and fire resistance in open-sided car parks.
The biggest proposal for residential design is a minimum of two stairs and two evacuation lifts in new residential buildings above 18 metres. It is not current guidance yet, so schemes on long programmes should keep their fire strategy under review.
What to do now
- Confirm your building control submission date and route.
- Record which version of Approved Document B the scheme relies on.
- Check when foundations or piling will start against the 18-month window.
- Test the design with a second stair if your position is uncertain.
- Review planning, cost and viability if the layout changes.
- On higher-risk buildings, build realistic Gateway 2 timescales into the programme.
Finding out late will cost far more than checking now.
Second staircase regulations FAQs
When did the second staircase regulations come into force?
They came into force in England on 30 September 2026. Building control applications made on or after that date need to follow the amended guidance.
Is planning permission enough to keep the old guidance?
No. The building control submission must have been made before 30 September 2026, and the work must be sufficiently progressed within the transitional period.
Are evacuation lifts now required?
Not under the current amendments, which cover how evacuation lifts should be designed where they are provided. A 2026 consultation has proposed evacuation lifts in new residential buildings above 18 metres.
Do existing buildings need a second staircase?
No. The change applies to new building work and material changes of use, not to occupied buildings. Owners of existing blocks should still keep their fire risk assessments and fire safety surveys up to date.
Get advice on your scheme
Bailey Partnership works with developers and housing providers on residential developments across England.
Our team can review your regulatory route, test the impact of a second stair and coordinate any design changes.
Contact Bailey Partnership to talk through your scheme.