Listed building consent: how the process works under the new NPPF
Listed building consent is needed for works that affect the special interest of a listed building, inside or out. Since new national planning policies took effect on 17 August 2026, the way councils assess harm to heritage has changed, and applications need to reflect that.
If you own or manage a listed building, or you are planning a heritage-led scheme, understanding the process before your design is fixed will save time and money.
Listed building consent: when do you need it?
Under the Planning (Listed Buildings and Conservation Areas) Act 1990, you need consent to demolish a listed building, or to alter or extend it in a way that affects its character as a building of special architectural or historic interest.
Listing covers the whole building, not just the front elevation. Interiors, fixtures and some older structures within the grounds can all be protected. The rules are the same for Grade I, Grade II* and Grade II buildings.
Works that often need consent include changes to:
- windows, doors and shopfronts
- internal walls and room layouts
- staircases, fireplaces and joinery
- roofs and external materials
- services that cut through historic fabric.
Internal works are the easiest to overlook. A project may need no planning permission at all and still need consent, which is a common issue with interiors in listed buildings. If in doubt, speak to your council’s conservation officer before starting.
Is it different from planning permission?
Yes. They are separate regimes, and a project can need one, both or neither. Planning permission does not replace listed building consent, so an extension to a listed building will usually need both.
Where both are needed, prepare them together so the planning, design and heritage cases line up. Our town planning and architecture teams regularly run the two side by side.
What changed in the NPPF in August 2026?
The new National Planning Policy Framework reorganised heritage policy into Chapter 20. The biggest change is that “less than substantial harm” is no longer a policy test.
Harm is now described as total loss, substantial harm or other harm. Under Policy HE5, applicants must say whether a proposal has a positive effect, no effect, causes harm (and how much) or results in total loss.
Policy HE6 says any harm to a designated heritage asset is a matter of considerable importance and weight. That harm is weighed against the public benefits of the scheme, and the framework gives securing the reuse of vacant listed buildings as an example. Substantial harm or total loss should be exceptional for Grade II buildings and wholly exceptional for Grade I and II*.
Does the statutory duty still apply?
Yes. The 1990 Act still requires decision-makers to have special regard to preserving a listed building, its setting and its features. The new NPPF confirms that it does not displace the statutory duties in the Act.
Heritage statements under the new NPPF
Labelling an impact “less than substantial” is no longer enough. A heritage statement now needs to explain clearly what matters about the building and what the proposal does to it.
What a listed building consent heritage statement should cover
- which parts of the building are significant, and why
- how the setting contributes to that significance
- which elements the works will affect
- whether the effect is positive, neutral, harmful or a total loss
- how any harm has been avoided or kept to a minimum.
The level of detail should match the importance of the building and the scale of the works. Assessing significance before design starts is far more effective than writing a justification afterwards.
How long does it take and what does it cost?
Councils normally have eight weeks from validation to decide an application. The whole process usually takes longer once you allow for pre-application advice, surveys, drawings, consultation, revisions and discharging conditions.
There is no application fee for listed building consent in England. You will still need to budget for drawings, surveys and specialist reports, and any planning application submitted alongside it carries its own fee.
Do repairs and energy upgrades need consent?
Genuine like-for-like repair often does not, but the line between repair and alteration can be fine. Changing materials or replacing historic fabric may still need consent. If you want certainty, a certificate of lawfulness of proposed works confirms formally that consent is not required.
Secondary glazing, insulation and heat pumps usually need consent, but they are often achievable. At York House in Penzance, a Grade II listed building, our team secured consent for secondary glazing and insulated linings, and every completed apartment reached at least EPC C.
The new NPPF also gives substantial weight to improving the energy efficiency of existing buildings, including heat pumps and solar panels. That strengthens the case for well-designed upgrades.
It matters for property value too. The government has confirmed it will remove the EPC exemption for heritage properties, with reformed EPCs due to launch in the second half of 2027.
What if work has been done without consent?
Carrying out unauthorised works to a listed building is a criminal offence, and the council can require the work to be reversed. Unauthorised changes can also cause problems when you come to sell.
If you discover past alterations during a purchase or refurbishment, get specialist advice before doing anything further.
When to bring in a historic building consultant
For small jobs, a conversation with the conservation officer may be enough. For larger or more sensitive schemes, heritage input from the start helps you keep what matters while still delivering the project.
Our historic building consultancy was established in 1995 and has worked with clients including English Heritage and Historic Royal Palaces. Our heritage projects include the Brook Theatre in Chatham and the conversion of a Grade II listed warehouse in Plymouth’s Barbican, where our proposals gained the support of the conservation officer and Historic England.
Listed building consent FAQs
Do I need listed building consent for internal works?
Yes, if the works affect the building’s special interest. Listing covers interiors as well as exteriors.
Is there a fee for listed building consent?
No. There is no application fee in England, although a separate planning application would carry a fee.
How long does listed building consent take?
Councils normally have eight weeks from validation. Allow extra time for preparation, consultation and any revisions.
Does the 2026 NPPF still use “less than substantial harm”?
No. Effects are now described as positive, no effect, harm, substantial harm or total loss, with the degree of harm set out clearly.
Can I replace windows in a listed building?
Usually only with consent. Repairing historic windows or adding secondary glazing is often the more acceptable option.