Gateway 2 applications in 2026: what has changed and what a compliant submission looks like

Admin

A Gateway 2 application for a new higher-risk building now takes a median of 22 weeks, down from 43 weeks a year ago, and the approval rate for new builds has climbed from 39% to 91%. Remediation projects have improved more slowly, and that gap now shapes how project teams should plan their submissions.

Gateway 2 is the building control approval that the Building Safety Regulator must grant before work can begin on a higher-risk building in England. It is a programme milestone with a hard stop attached, not an administrative formality. The system has faced well-publicised delays, but the latest figures show performance improving, and how much improvement a project sees depends on the type of work and the quality of the application submitted.

What is a Gateway 2 application?

A Gateway 2 application is an application for building control approval for higher-risk building work, submitted to the Building Safety Regulator, which acts as building control authority for these projects.

Under the design and construction regime, a higher-risk building is a building in England at least 18 metres high or with at least seven storeys, containing at least two residential units or serving as a hospital or care home.

Before construction begins, the client, or someone authorised to act on their behalf, must submit a Gateway 2 application. It must show how the proposed work will comply with the Building Regulations and how that compliance will be managed throughout the project. The requirement forms part of the dutyholder regime introduced by the Building Safety Act 2022, which sits alongside the separate principal designer duties under CDM.

How long does a Gateway 2 application take in 2026?

The headline figure of 22 weeks does not tell the whole story. Gateway 2 timescales vary considerably between new builds, remediation schemes, internal refurbishment and NHS projects.

New higher-risk buildings

When the Building Safety Regulator established its Innovation Unit in August 2025 to handle new-build applications exclusively, the median determination time was 43 weeks and the approval rate was 39%. Twelve months later, the median determination time has fallen to 22 weeks and the approval rate has risen to 91%.

Remediation and internal refurbishment

Progress has been slower for remediation. Over the same period, the median determination time for external remediation fell from 43 weeks to 34 weeks, and the approval rate rose from 47% to 85%.

Internal refurbishment has an overall median determination time of 32 weeks and an approval rate of 77%. Applications submitted during 2026 have a median determination time of 16 weeks. The higher overall figure still includes older cases that are only now being closed, so the recent number is the better guide to what a new submission can expect.

NHS projects

NHS work is now tracked separately for the first time. The category covers hospital projects ranging from maintenance to new facilities, and currently shows an approval rate of 84% and a median determination time of 24 weeks. For teams delivering healthcare schemes, this is a benchmark that did not exist a year ago.

Where the Regulator is heading

London accounts for roughly 65% of new-build applications in progress and approves around 93% of them, above the national picture. About 1,547 Gateway 2 applications remain in progress nationally.

The Building Safety Regulator became a standalone body sponsored by the Ministry of Housing, Communities and Local Government in January 2026, part of a longer-term move towards a single construction regulator. Its strategic plan targets responses within 18 weeks for non-complex new-build applications by the end of March 2027, and 12 weeks for non-complex remediation.

Those are targets rather than guaranteed Gateway 2 timescales. Complexity, application quality and requests for further information will continue to affect how long a determination takes.

What does a Gateway 2 application need to include?

A Gateway 2 application must demonstrate three things: that the proposed work will comply with the Building Regulations, that the project will be managed effectively, and that the people carrying out key duties are competent to do so.

Supporting documentation typically includes detailed plans and drawings, a Building Regulations compliance statement, a competence declaration, construction and change control plans, a mandatory occurrence reporting plan, and a fire and emergency file. A partial completion strategy and a staged work statement are added where relevant.

These documents must be consistent with one another. Applications struggle where drawings, specifications and statements conflict, rest on unresolved assumptions, or fail to explain clearly how compliance will be achieved.

Why are Gateway 2 applications rejected?

The Building Safety Regulator may reject an application if there is not enough information to demonstrate compliance, or if the arrangements for managing compliance are inadequate.

Construction projects have historically progressed while some design packages were still in development. Under the Gateway 2 regime, that becomes a problem when the missing information is fundamental to demonstrating compliance.

Common reasons for rejection include:

  • Incomplete or inconsistent design information.
  • Unresolved design assumptions.
  • Poor coordination between architectural, structural and building services information.
  • Building Regulations requirements that have not been clearly addressed.
  • Fire strategy information that does not align with the drawings.
  • Inadequate change control procedures.
  • Weak evidence of dutyholder competence.

Staged applications and approval with requirements

Gateway 2 is not always a straightforward approve or reject decision. Two routes offer more flexibility than many project teams expect.

A staged Gateway 2 application divides the work into defined stages, with detailed information submitted for each stage before that work begins. The first stage of a single-tower scheme might cover foundations, basement work and the ground-floor structure. Staging does not let construction run ahead of the Regulator: each stage is assessed separately, work cannot begin until that stage is approved, and staging is considered case by case.

An approval with requirements allows work to begin on approved elements while others are held back until further information has been supplied or a specific issue resolved.

Neither route substitutes for a complete and coordinated application.

What happens when the design changes after Gateway 2 approval?

The information approved at Gateway 2 becomes the project’s agreed documents. Subsequent changes are treated as controlled changes and managed through the approved process, with a change log maintained throughout construction. Notifiable and major changes must be reported to the Building Safety Regulator, and where a change is classed as major, work on the affected part must stop until it has been approved.

Design decisions made before submission should therefore be realistic and buildable. Submitting one solution to secure approval while expecting to redesign it later creates programme risk rather than avoiding it.

How does Gateway 2 interact with Part L 2026?

Part L 2026 takes effect for higher-risk building work on 24 September 2027. To remain under the previous standard, a valid Gateway 2 application must have reached the Building Safety Regulator before that date, and must not later be rejected or allowed to lapse.

That places the energy strategy and the Gateway 2 application on the same critical path. Late changes to the façade, building services or renewable systems affect both. The Building Safety Levy adds a further cost consideration within the same window.

How can project teams prepare a stronger Gateway 2 application?

Treat Gateway 2 as a design management process rather than a final submission exercise. Before applying:

Confirm whether the project falls within the higher-risk building regime, and build Gateway 2 into the programme early with realistic time for review and queries.

Coordinate architectural, structural, fire and building services information before submission.

Identify unresolved assumptions and confirm the compliance statement reflects the design as it stands.

Make sure dutyholders understand their responsibilities and competence requirements.

Establish a practical change control process before construction begins, and consider whether a staged application would serve the project better than an incomplete submission for the whole scheme.

Plan beyond Gateway 2, including information management, site inspections and Gateway 3.

Gateway 2 FAQs

How long does a Gateway 2 application take in 2026?

The median determination time is 22 weeks for new higher-risk buildings and conversions, 34 weeks for external remediation and 32 weeks for internal refurbishment, though internal refurbishment applications submitted during 2026 are running at a median of 16 weeks.

Who submits a Gateway 2 application?

The client, or someone authorised to act on the client’s behalf. The wider dutyholder team is also responsible for demonstrating and maintaining compliance.

Can construction start before Gateway 2 approval?

No. Relevant work must not begin until the Building Safety Regulator has approved the application. Validation alone does not authorise construction.

Why is remediation slower than new-build work?

New-build applications have been handled by a dedicated Innovation Unit since August 2025, nearly halving median determination times. Improvements to remediation began later and from a larger backlog.

What happens if a Gateway 2 application is rejected?

The Building Safety Regulator will explain the reasons for its decision. Applicants can request a review and may subsequently have a right of appeal to the First-tier Tribunal.

Talk to us about your Gateway 2 application

Queue position is outside a project team’s control. The completeness of the package is not, and applications submitted during 2026 are being determined faster than the older cases still working through the system.

If you have a scheme approaching Gateway 2, Bailey Partnership can review the package, identify missing or inconsistent information, and coordinate the building safety evidence across disciplines. Contact us to discuss your project.